Press reviews & construction diary
Read up on all the latest news
Take a peek behind the scenes and follow the construction of our new Hotel Die Post am Ortler step by step in our construction diary. In addition to our successful building project, we are also happy to report on successes and news in the hotel and tourism industry. Read on for the latest information on our 4-Star Superior hotel in South Tyrol!
Construction phase 1
April to July 2024
- Foundations of the indoor and outdoor pool, building shell, plant rooms
- Changes to pond and excavation works in the garden
Construction phase 2
November to December 2024
- Preparatory work for the wellness area
- Completion of plant rooms
Construction phase 3
April to December 2025
- Extension and new construction of the entire hotel – the historic part remains intact
- Refurbishment of the entire ground floor with entrance, reception, hotel lounge, bar and common rooms
- Refurbishment of restaurant and “Stuben”, buffet areas and kitchen
- 20 new rooms and luxury suites – in total: 71 rooms and suites
- Approx. 1,800m² spa with reception, wellness & beauty, quiet rooms
- Approx. 3,300m² garden, outdoor pools, swimming pond, sun islands and sun terraces
- New fitness lounge with top-of-the-range machines
- Yoga room, seminar room, multi-purpose room
- Children’s play areas and room for youngsters
- Lots of new ideas for indulgence and relaxation